In large construction and fabrication spaces, overhead/bridge cranes do the heavy lifting—literally. This practical guide takes you behind the scenes of a mega-project crane install. You’ll see hoist and trolley setup—all explained in clear, real-world language.
Overhead Crane, Defined
An overhead crane rides on parallel runways anchored to a building frame, carrying a trolley-mounted hoist for precise, vertical picks. The result is smooth X-Y-Z motion: and lift via the hoist.
They’re the backbone of heavy shops and assembly lines, from beam handling to turbine assembly.
Why they matter:
Controlled moves for large, expensive equipment.
Huge efficiency gains.
Repeatable, precise positioning that reduces damage.
Support for pipelines, structural steel, and big machinery installs.
System Components We’re Installing
Runways & rails: runway girders with crane rail and clips.
End trucks: motorized gearboxes for long-travel.
Bridge girder(s): cambered and pre-wired.
Trolley & hoist: reeving, hook block, upper limit switches.
Electrics & controls: power supply, festoon or conductor bars.
Stops, bumpers & safety: end stops, buffers, travel limits.
Depending on capacity and span, you may be dealing with modest shop lifts or major industrial picks. The choreography is similar, with heavier rigs demanding extra controls and sign-offs.
Before the First Bolt
A clean install is mostly planning. Key steps:
Drawings & submittals: Approve general urban construction arrangement (GA), electrical schematics, and loads to the structure.
Permits/JSAs: Permit-to-work, hot work, working at height, rigging plans.
Runway verification: Survey columns and runway beams for straightness, elevation, and span.
Power readiness: Lockout/tagout plan for energization.
Staging & laydown: Mark crane components with ID tags.
People & roles: Brief everyone on radio calls and stop-work authority.
Millimeters at the runway become centimeters at full span. Measure twice, lift once.
Getting the Path Right
If rails are off, nothing else will run true. Targets and checks:
Straightness & elevation: shim packs under clips to meet tolerance.
Gauge (span) & squareness: Check centerlines at intervals; confirm end squareness and expansion joints.
End stops & buffers: Install and torque per spec.
Conductor system: Keep dropper spacing uniform; ensure collector shoe reach.
Record as-built readings. Misalignment shows up as crab angle and hot gearboxes—don’t accept it.
Lifting the Bridge
Rigging plan: Softeners protect painted flanges. Taglines for swing control.
Sequence:
Install end trucks at staging height to simplify bridge pick.
For double-girder cranes, lift both girders with a matched raise.
Use drift pins to align flange holes; torque to spec.
Measure diagonal distances to confirm squareness.
Prior to trolley install, bump-test long-travel motors with temporary power (under permit): ensure correct rotation and brake release. Re-apply LOTO once checks pass.
Hoist & Trolley
Trolley installation: Mount wheels, align wheel flanges, set side-clearances.
Hoist reeving: Lubricate wire rope; verify dead-end terminations.
Limits & load devices: Set upper/lower limit switches.
Cross-travel adjustment: Align trolley rails on a double-girder.
Pendant/remote: Install pendant festoon or pair radio receiver; function-test deadman and two-step speed controls.
A smooth trolley with a quiet hoist is a sign of good alignment. Don’t mask issues with higher VFD ramps.
Electrics & Controls
Power supply: Conductor bars with collectors or a festoon system.
Drive setup: Program VFDs for soft starts, decel ramps, and brake timing.
Interlocks & safety: Zone limits near doors or mezzanines.
Cable management: Secure junction boxes; label everything for maintenance.
Future you will too. Photos of terminations help later troubleshooting.
Trust but Verify
Inspection Test Plan (ITP): Hold/witness points for rail alignment, torque, electrical polarity, limit settings.
Torque logs: Re-check after 24 hours if required.
Level & gauge reports: Note any corrective shims.
Motor rotation & phasing: Document bump tests.
Functional tests: Anti-collisions and zone interlocks.
A tidy databook speeds client acceptance.
Proving the System
Static load test: Hold at mid-span and near end stops; monitor deflection and brake performance.
Dynamic load test: Travel long-run, cross-travel, and hoist at rated speed with test load.
Operational checks: Limit switches trigger reliably; overload trips; horn/beacon function.
Training & handover: Maintenance intervals for rope, brakes, and gearboxes.
Only after these pass do you hand over the keys.
Everyday Heavy Lifting
Construction & steel erection: handling long members safely.
Oil & gas & power: moving heavy pumps, skids, and pipe spools.
Steel mills & foundries: large part transfer.
Warehousing & logistics: bulk material moves with minimal floor traffic.
Once teams learn the motions, cycle times drop and safety improves.
Controls that Matter
Rigging discipline: dedicated signaler and stop-work authority.
Lockout/Tagout: test before touch every time.
Fall protection & edges: approved anchor points, guardrails on platforms, toe boards.
Runway integrity: regular runway inspection plan.
Duty class selection: overspec when uncertainty exists.
Safety isn’t a stage—it's the whole show.
Keep It Rolling
Crab angle/drift: verify end-truck wheel diameters and gearbox mounts.
Hot gearboxes: misalignment or over-tight brakes.
Rope drum spooling: dress rope and reset lower limit.
Pendant lag or dropout: antenna placement for radio; inspect festoon collectors.
Wheel wear & rail pitting: add rail sweeps and check clip torque.
A 10-minute weekly check saves days of downtime later.
FAQ Snippets
Overhead vs. gantry? Choose per site constraints.
Single vs. double girder? Singles are lighter and cheaper; doubles carry heavier loads and give more hook height.
How long does install take? Scope, bay readiness, and tonnage rule the schedule.
What’s the duty class? FEM/ISO or CMAA classes define cycles and service—don’t guess; size it right.
What You’ll Take Away
Students and pros alike get a front-row seat to precision rigging, structural alignment, and commissioning. You’ll gain a checklist mindset that keeps cranes safe and productive.
Looking for a clean handover databook index you can reuse on every project?
Grab the installer pack so your next crane goes in cleaner, faster, and right the first time. Bookmark this guide and share it with your crew.
...